FCC Regenerator TurnaroundFCC Regenerator Turnaround (Unit 55 – 55-R-202), Heydar Aliyev Oil Refinery, Baku
We are pleased to announce the successful completion of the FCC Regenerator Turnaround at Unit 55 (55-R-202), as part of TAR2024 at the Heydar Aliyev Oil Refinery (HAOR), Baku.
Scope of Work Included:
-
Complete dismantling and installation of 1st and 2nd stage cyclones
-
Replacement of air distribution headers, injection nozzles, and shut-off valves
-
Internal repair works on the regenerator shell and spherical dish
-
Execution of NDT inspections, welding, lifting, scaffolding, and confined-space operations
Project Execution:
-
The work was carried out under strict 24/7 shift operations
-
Core activities were completed in just 25 days, following a 1-month pre-TAR mobilization phase
Key Outcomes:
-
Full adherence to HSE and QA/QC requirements
-
Strong collaboration with SOCAR’s Integrity and Reliability departments
We thank our dedicated team and project partners for ensuring a safe and efficient turnaround.
Client: SOCAR Downstream
Location: Heydar Aliyev Oil Refinery (HAOR), Baku
Duration: 1-month mobilization + 25 days execution
Year: 2024